Steel Jacket News

Image courtesy Jan de Nul

Second Sea Cable Lay for 'West Alpha' Completed

coast with the UTV1200 unmanned cable-laying vehicle on board. As soon as the Isaac Newton set sail, the cable slowly unwound from the large turntable on board. Later followed by the Adhémar de Saint-Venant for the steering of the UTV1200, which then laid the cable in the seabed.TenneT had the steel jacket for the transformer platform placed on the seabed 50 km off the coast of Egmond aan Zee last August. The turbines of the wind farm will soon be connected to this socket. With the retraction of the last cable via the cable deck, the job is done for the contractor combination.Once the tests are

“A new challenge is the installation of big windmills. Big windmills today are 13 MW, 14MW. They are going up to 15 MW and people talk about 20 MW, so we have developed a system that can handle up to 20 MW. By weight it’s nothing, but in terms of technical challenge, it’s very interesting because the windmills are very big, the blades are extreme sizes and installation is at enormous heights. We think Pioneering Spirit is a big vessel, but if you take the biggest windmill of the future, she is t

Edward Heerema – Dutch Courage with Single-minded Focus

then upend jackets onto the vessel’s deck, with the jacket then resting on top of the beams, for transport, without needing sea fastening.Test lifts of the system were carried out in late February into early March, and systems testing will continue, leading up to lifting out the eight-legged steel jacket of Ninian Northern, 240 miles east of Aberdeen in the northern North Sea, scheduled for April.Ninian Northern, which came on stream in 1980, ceased production in 2017 and saw its topsides removed, by Pioneering Spirit, in 2020. The remaining jacket sits in 141m water depth, making it a substantial

Gas pioneer Heimdal Turns 30

in 1971 that the Pan Ocean Group was awarded the production licence for the field in the second licensing round. The first well was drilled between July and December 1972 and proved to have both gas and condensate reserves. When it commenced production on 3 December 1985, Heimdal was the largest steel jacket  on the Norwegian continental shelf. Production of gas and condensate proceeded at reasonably steady annual rates in the period from 1986 to 1996. Subsequent declining production led to plans to use Heimdal as an important transit and processing centre for gas from other fields. A riser

Huldra platform (Photo: Statoil)

Huldra Platform Recycling Contract Awarded

Marine Contractors Nederland SE.   The contract for disposal and recycling of the platform has been awarded to AF Offshore Decom AS, a subsidiary of AF Gruppen ASA   The total weight of the platform is approximately 10,000 tons, distributed over a 5,000 ton topside and a 5,000 ton steel jacket. It is expected that more than 95 percent of the platform will be recycled.   The plan is to remove the Huldra platform during 2019 with the subsequent disposal and recycling work taking place at AF Offshore Decom’s environmental base in Vats, Norway within the first half of 2020

Increased Norwegian Content for Johan Sverdrup Platform

venture with KBR won the contract for the complete delivery of the utility and living quarter (ULQ) topside. The platform also includes the advanced control room and the sental systems all installations on the field. In addition, Kvaerner is responsible for complete deliveries of three of the four steel jacket substructures for this phase of the Johan Sverdrup development. The main scope of the steel jackets will be constructed at Kvaerner's specialised facility in Verdal, Norway. For the complete delivery of the 19 000 tonnes topside, a large portion of the work will be executed at the company's

Statoil, Partner Submit PDO for Oseberg Vestflanken 2

reduced total investment costs by around NOK 1 billion following the concept selection earlier this year. Maturing of the resource base, leading to higher volumes, has also helped realise the project. “The costs of subsea templates have tripled during the last 10 years. Platform wells on a steel jacket lead to considerable cost reductions and secure a robust project economy,” says senior vice president for the projects cluster in Statoil Torger Rød. Oseberg Vestflanken 2 is an important element in further developing the Oseberg infrastructure for the future, and is a result of

Statoil Contracts for Two Johan Sverdrup Jackets

; On behalf of the Johan Sverdrup licence, Statoil is today awarding contracts for two Johan Sverdrup jackets to Kvaerner Verdal and Dragados Offshore S.A. The contract awarded to Kvaerner Verdal has a value of approximately NOK 1 billion and covers engineering, fabrication and construction of the steel jacket for the Johan Sverdrup processing platform. Weighing 17,700 tonnes, the jacket will be constructed at the yard in Verdal and installed on the Johan Sverdrup field in the summer of 2018. “This is the third delivery based on the letter of intent signed by Statoil and Kvaerner for delivery

(Image: Statoil)

Kværner Secures Another Johan Sverdrup Contract from Statoil

Statoil has signed Kværner Verdal on board for another complex steel jacket delivery for the Johan Sverdrup drilling platform, Statoil announced today. The contract, awarded by Statoil on behalf of the Johan Sverdrup partnership, is an execution of the letter of intent signed by Statoil and Kværner for delivery of two jackets for Johan Sverdrup located on the Utsira High in the North Sea, 155 kilometers west of Stavanger. “An important part of the original letter of intent between Statoil and Kværner for delivery of steel jackets implied that the partners were to cooperate

Johan Sverdrup Construction Begins

thoroughly for a long time making the preparations for this exciting and complex project. It feels great now that we’ve started construction on one of the biggest industrial projects in Europe,” says senior vice president for the Johan Sverdrup development project, Kjetel Digre. The steel jacket now being built at Kværner Verdal will weigh 26 500 tonnes, making it the biggest steel jacket in Europe. “The steel jacket will also be one of the most complex ever built by the industry. Not only will we route the land-based power through the jacket, we’ll also be controlling

The February 2024 edition of Marine Technology Reporter is focused on Oceanographic topics and technologies.
Read the Magazine Sponsored by

The Clock is Ticking on the Doomsday Glacier

Marine Technology Magazine Cover Mar 2024 -

Marine Technology Reporter is the world's largest audited subsea industry publication serving the offshore energy, subsea defense and scientific communities.

Subscribe
Marine Technology ENews subscription

Marine Technology ENews is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

Subscribe for MTR E-news