Minesto Gets OK for Tidal Kite Installation in Faroe Islands

April 1, 2020

Marine energy developer Minesto has said it been granted all necessary permits and consents for the installation of two grid-connected tidal kite systems in Vestmannasund, Faroe Islands.

The granted permits and consents cover two DG100 tidal kite systems which will be installed in Vestmannasund in a collaboration between Minesto and the Faroese electric utility company SEV. 

Image Credit: Minesto
Image Credit: Minesto

Minesto has been granted public funding totaling approx. €3.5 million through the EU's EIC Accelerator and the Swedish Energy Agency for the implementation of the Vestmannasund project and the development of the DG100 marine energy converter.

"We have had great support by SEV and the Faroese authorities to reach this crucial achievement. SEV has made terrific work to secure all necessary permits for our first installations in the Faroe Islands through a very efficient process", said Martin Edlund, CEO of Minesto.

Earlier this month, Minesto announced that it is carrying out onshore commissioning testing of the DG100 tidal kite system and at the cable landing site in Vestmannasund, onshore infrastructure works are currently underway by SEV to enable the grid connection of Minesto's kites. In addition, Minesto also announced the establishment of a Faroese subsidiary which will facilitate and further develop ongoing and future installations of the company's marine energy converters in the Faroe Islands.

"We are pleased with the progress made in the joint project, which will pave the way for a significant addition of predictable renewable electricity generation in the Faroe Islands", said Martin Edlund.

Related News

Over 150 Specialist Subsea Jobs Up for Grabs at Rovco and Vaarst Aker BP Opts for Optime Subsea’s ROCS Saipem’s Hydrone-R Marks Subsea Milestone at Equinor’s Njord Field UTEC Gets Offshore Wind Survey Job in Taiwan Mocean Energy’s Blue X Wave Device and Verlume’s Halo Battery Come Ashore