Storage Tanks Installed on World’s First FLNG

October 31, 2013

Photo: Wison
Photo: Wison

Wison Offshore & Marine reports that it successfully completed the installation of the three LNG storage tanks into the hull of the Caribbean FLNG project, considered a significant  milestone in the delivery of the world’s first floating LNG production unit.

With this major activity completed, the pathway is clear for installing the barge deck and topsides on the project.

The Caribbean FLNG project, being supplied to EXMAR by Wison Offshore & Marine under an EPCIC contract, will be installed off the coast of Colombia.  The project started fabrication at the end of 2012 and is planned to be in operation the first quarter of 2015 as the world’s-first FLNG vessel. The project is progressing on schedule, and expected to be mechanically complete in April 2014 with sail away in the fall of 2014. 

Supplied by TGE, the combined capacity of the three LNG storage tanks is 16,100 cubic meters, with a net weight of around 395 tons each. The complete tanks were hoisted by two 400-ton goliath gantry cranes in WOM’s drydock.

wison.com

 

Related News

TGS and Chevron Sign Data Acquisition Deal Venterra Rolls Out V-LiDAR Fleet for Offshore Wind Surveys China’s Ming Yang Unveils Plans for 50MW Ultra-Large Floating Wind Turbine 50 Years of Women in Navy Diving: Advancing Opportunity in Tandem with Technology Indeximate Demos Cable Health Monitoring Tech on RWE Subsea Cables