Johan Sverdrup News

Luis Araujo, CEO, Aker Solutions

Aker Solutions Revenues Up 8%

, with studies from overseas markets equaling 35 percent of the total."In 2018, we saw a record number of studies and front-end engineering work for larger and more complex projects than previous years - a positive sign of more work to come," said Araujo. "As we have already seen at Johan Sverdrup, Johan Castberg and Troll, early involvement puts us in a strong position to secure more work."In January 2019, Aker Solutions acquired the remaining 30 percent of Brazilian C.S.E. Mecânica e Instru-mentação Ltda, having bought the first ownership stake of 70 percent

(Photo: Aquaterra Energy)

Aquaterra Bags More Johan Sverdrup Work

Aquaterra Energy announced Thursday it has been awarded a contract by Equinor to deliver early well construction operations for the next 16 wells of the Johan Sverdrup field development in the Norwegian North Sea.The award follows Aquaterra Energy’s Phase I Tie-Back project for the engineering of nine complete strings of centralizers and tieback engineering services, which were delivered in Q3 2018.Under the new contract, the company will supply its Well Start solution to engineer conductor guide, cellar deck and internal centralizers for the field to ensure conductor performance for the 50-year

(Photo: NKT)

NKT to Supply Cables for Johan Sverdrup 2

Denmark-based cable supplier NKT said it has received a letter of award from Norway's Equinor to supply and install a cable system of 200 kilometers of 80 kV high-voltage DC offshore power cables for the second phase of the Johan Sverdrup oil field development project in the Norwegian North Sea.The award is conditional upon finalization of the formal contract which is likely to take place within a few weeks, NKT said. The contract value is expected to be approximately EUR 110 million, corresponding to roughly EUR 82 million in standard metal prices.The cable system comprises two 200 km of cables

Illustration / TRY courtesy Equinor

Aker BP CEO Predicts Fast Johan Sverdrup Ramp-up

Aker BP, a partner in Norway's giant Johan Sverdrup oilfield, expects a fast ramp-up of production when the initial development phase ends in late 2019, its chief executive said on Thursday."I think it will be done in a few months, because the production per well is so high," Karl Johnny Hersvik told Reuters on the sidelines of an energy conference.Johan Sverdrup Phase 1 will have capacity to produce 440,000 barrels of oil equivalents per day (boed), while the second phase, starting production in 2022, is expected to further boost output to 660,000 boed.Sweden's Lundin Petroleum

Saipem Castorone at the Johan Sverdrup field in the North Sea. (Photo: Bo B. Randulff / Roar Lindefjeld / Equinor ASA)

Norway’s Largest Oil Pipeline Now in Place

Late last week, Norway’s largest and longest pipeline reached the Johan Sverdrup field in the North Sea.The last pipe of what is now Norway’s longest and largest oil pipeline was installed by the vessel Saipem Castorone, right next to the riser platform at the Johan Sverdrup field. The 36-inch pipeline extends 283 km from the Mongstad oil terminal outside Bergen to the giant field in the North Sea.“We have together with our supplier Saipem succeeded in laying the oil pipeline to Johan Sverdrup without any serious incidents. It has been a significant operation, involving more than 600

Photo: Harald Pettersen / Equinor

Equinor to Boost Drilling to Extend Norwegian Shelf Life

the company believes its Norwegian resource potential is as large today as it was a decade ago, each prospect is smaller, making it necessary to drill more and cheaper wells, exploration chief Tim Dodson told a news conference.The company is currently investing heavily to develop the $15 billion Johan Sverdrup oilfield, which will be completed in two stages between 2019 and 2022, as well as the Arctic Johan Castberg and an extension of the Troll gas field."We need to start now. After 2022 there are currently few big projects remaining. The choices that we, the authorities, and the industry make

Photo: Equinor

Aker Solutions Bags Work On Johan Sverdrup Offshore Norway

Aker Solutions has, in collaboration with Kvaerner, secured additional hook-up and commissioning work for Equinor's Johan Sverdrup field offshore Norway.Equinor has exercised an option in the Johan Sverdrup Riser platform hook-up contract  awarded in January 2017 for Aker Solutions to perform hook-up and commissioning assistance of the field's utility and living quarter platform, as well as the preparatory offshore work connected with the phase two modifications of the riser platform."We are delivering well and on schedule on the hook-up work that we are currently performing on the

Phase 2 will add a fifth platform to the ‘The North Sea Giant’, Johan Sverdrup. Credit: Equinor

Kongsberg Wins Johan Sverdrup Phase 2 Contract

Equinor Energy AS has contracted Kongsberg Maritime to deliver the Safety and Automation Systems (SAS) for the recently announced phase 2 of the Johan Sverdrup development in the Norwegian North Sea.The phase 2 agreement includes delivery of SAS and digital technology for a new processing platform, which is due to start production in 2022. Kongsberg Maritime will also extend and modify already delivered systems for the field center, in addition to providing three Subsea Production System tie-backs and technology solutions for shore power at Haugsneset, near Haugesund.The core scope of supply for Johan

Map Lille Prinsen discovery (Photo: Equinor)

New Oil Discovered in the North Sea

Exploration, Norway & UK.“This is a good discovery which we expect will be commercial. In addition, the results from the drilling indicate an upside potential in this discovery,” Ashton pointed out.The Lille Prinsen well is located 200 kilometers west of Stavanger and northwest of the Johan Sverdrup field. The discovery in the well’s main target is estimated to contain 15-35 million barrels of recoverable oil.There was made one additional discovery with very good reservoir quality over the main discovery, but the volume in this discovery has not been evaluated. The well also appraised

Photo: Espen Rønnevik / Roar Lindefjeld

Johan Sverdrup Drilling Platform Installed

The 22,000-tonne topside for the drilling platform was lifted into position in one single lift on the Johan Sverdrup field last weekend. Equinor and the Johan Sverdrup partners are the first users in the world of this ground-breaking technology.On Thursday, May 31, the topside for the Johan Sverdrup drilling platform sailed from the Aibel yard in Haugesund to Bømlafjorden at Stord.Here the 22,000-tonne steel structure was transferred from the barge to Pioneering Spirit, the world’s biggest heavy-lift vessel. All set for the 11-hour journey to the jacket waiting for its topside on the

The cable-laying vessel NKT Victoria at the Johan Sverdrup converter station at Haugsneset near Kårstø.(Photo: Øyvind Gravås - Woldcam / Statoil)

Efficient Cable Installation Slashes Emissions at Johan Sverdrup

The laying of the cable supplying Johan Sverdrup with power from shore started last week. This helps make the North Sea giant one of the oil and gas fields with the lowest CO2 emissions worldwide.On Wednesday last week the cable-laying vessel NKT Victoria began laying the cables that will supply the Johan Sverdrup field with power from shore.The starting point was the Johan Sverdrup converter station at Haugsneset near Kårstø, and by the end of May the vessel will have laid nearly 200 kilometers of power cables out to the field in the North Sea.Bundled with the power cables, a fiber-optic

(Photo: Statoil)

Johan Sverdrup ROV Contract Awarded

Statoil has awarded IKM Subsea a services contract for ROVs on at the Johan Sverdrup platform commencing in the third quarter of 2018.The contract was won in a competition with other suppliers through an e-auction event that was performed as one of the final stages of the tendering process.The scope of work consists of provision of ad-hoc ROV operations to support drilling activities on the Johan Sverdrup field. The contract duration is six years plus additional options.

The riser platform is one of four platforms that make up the field centre on the Johan Sverdrup field in Phase 1 of the project Photo credit Statoil

First Johan Sverdrup Topside Installed

With the last module of the Johan Sverdrup riser platform lifted into place, the first of four topsides of the next North Sea giant has been installed.“It’s a special feeling to see the first Johan Sverdrup platform in place, even a few days ahead of the plan set more than three years ago – all without any serious incidents along the way. This is a testament to the high quality in execution of the project so far, which again is a result of the good collaboration between thousands of people at our suppliers, partners and Statoil,” said senior vice president for Johan Sverdrup

Statoil signs letters of intent for Johan Sverdrup phase 2 with Aibel and Aker Solutions-Kværner joint venture Image Statoil

Statoil Inks LOI for Johan Sverdrup Phase 2

Statoil, on behalf of the Johan Sverdrup partnership, signed a letter of intent with Aibel for the construction of the processing platform topside for phase 2 of the project. A letter of intent for field center modifications is also issued to a joint venture of Aker Solutions and Kværner. Total value is estimated at more than NOK 11 billion ($1.4 billion).   Phase 1 of the Johan Sverdrup development is well underway with planned startup in late 2019. To promote synergies, continuity and a holistic development of the entire field the Johan Sverdrup partnership is issuing letters of intent

Statoil Image (Photo courtesy of Trellborg)

Trelleborg Wins Contract for Johan Sverdrup Oil Field

Trelleborg’s engineered products operation has announced it has been awarded a contract for the supply of elastomeric bearings to Statoil’s Johan Sverdrup oil field, Norway's largest offshore development in the past three decades.   Located on the Utsira Height in the North Sea, 160 kilometers west of Stavanger, the Johan Sverdup oil field will be operated by electrical power generated onshore, significantly reducing offshore emissions of climate gases. Daily production during the project’s first phase is estimated at 440,000 barrels per day, while peak production is estimated

Norway Wants Oil Companies to Use Technology to Boost Output

as a regulator can include conditions also for the use of EOR when approving development plans," she said. Norway's crude oil production has halved from a peak of 181 million cubic metres in 2000 to 94 million cubic metres in 2016. The regulator has already asked the partners in the giant Johan Sverdrup field offshore Norway to carry out a pilot project that would inject water mixed with polymers to aid recovery when the field starts production in 2019. "Traditionally EOR was regarded as tail production technology, but we think that the earlier the better, also in this particular case

(Image: Tampnet)

Tampnet Awarded Johan Sverdrup Contract

Tampnet, provider of high-capacity, low-latency based telecommunication infrastructure and services for the offshore oil and gas industry, was awarded a contract by Statoil for connecting the Johan Sverdrup field to their existing 2,500km subsea fiber infrastructure in the North Sea. This contract and turn-key project will optimize and strengthen the telecommunication infrastructure for this modern and digitalized field development.   Tampnet said its offshore network is built with continuous improvement and expansion in mind. Hence, throughout the North Sea the company has a number of potential

Marine Technology Magazine Cover Jan 2019 - Underwater Vehicle Annual

Marine Technology Reporter is the world's largest audited subsea industry publication serving the offshore energy, subsea defense and scientific communities.

Subscribe
Marine Technology ENews subscription

Marine Technology ENews is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

Subscribe for MTR E-news